Indoor and outdoor equipment models, orientation, supports, and clearances are correct
Critical itemUnits should match approvals and remain stable, drainable, serviceable, and clear of airflow restrictions.
A pre-startup heat-pump installation checklist for matched equipment, mounting and clearances, refrigerant line set, electrical service, condensate, ducts, filters, sensors, controls, auxiliary heat, weather protection, penetrations, and permit readiness before the system is energized and commissioned.
6 items to check
Units should match approvals and remain stable, drainable, serviceable, and clear of airflow restrictions.
Line sizes, length, elevation, joints, evacuation preparation, insulation, and penetration sealing should follow instructions.
Electrical work should match nameplate and adopted requirements.
Condensate should drain reliably without damaging the building or creating concealed leaks.
Air and control connections should support the approved sequence and service access.
The installation should be complete enough for safe commissioning and official inspection.
Use after equipment and connected work are installed but before final startup. This page verifies visible installation readiness; qualified technicians must perform refrigerant and energized tests. Do not open energized equipment, handle refrigerant, defeat safety controls, or enter unsafe attics or crawlspaces. Require licensed or qualified HVAC and electrical work where applicable.
A pre-installation duct checklist for accessible condition, leakage, sizing, static-pressure risk, return paths, room airflow, insulation, supports, contamination, filter arrangement, abandoned ducts, and repair scope before new HVAC equipment is connected to an unsuitable distribution system.
A final-payment commissioning checklist for proving HVAC or heat-pump airflow, external static pressure, refrigerant charge, temperature and humidity operation, condensate, controls, auxiliary heat, room delivery, noise, fault codes, documentation, and correction closure after installation.
An apples-to-apples HVAC replacement proposal checklist for equipment capacity and efficiency, load-calculation basis, ducts, electrical work, refrigerant lines, condensate, controls, permits, removal, commissioning, warranties, rebates, schedule, and payment terms before contractor selection.
A homeowner review checklist for confirming that heating and cooling loads use the actual home, climate, envelope, infiltration, ventilation, duct location, room-by-room needs, design temperatures, internal gains, and equipment performance before HVAC or heat-pump equipment is ordered.