Roof deck condition after tear-off checklist

A concealed-stage checklist after old roofing is removed and before underlayment covers the roof deck, focused on full exposure, sheathing or plank condition, moisture and leak evidence, support and fastening, documented replacement quantities, structural escalation, and approval to proceed.

6 items to check

Inspection progress0 of 6
0%

All contracted roof areas are exposed enough to evaluate the substrate

Critical item

Old roof covering, underlayment, loose fasteners, debris, and concealed patch materials should be removed as required by the contract so the deck and critical interfaces can be evaluated before new materials are installed.

Rot, delamination, swelling, broken boards, soft areas, and active moisture are identified

Critical item

Decking should provide a sound, dry, compatible fastening substrate for the selected system. Deteriorated or wet material and the water source should be evaluated rather than simply covered.

Deck support, panel edges, plank gaps, fasteners, and surface plane suit the roof system

Critical item

Sheathing or boards, spans, thickness, edge support, gaps, fastener condition, transitions, and surface plane should comply with the adopted requirements, approved repair details, and selected roof-covering instructions.

Sagging, damaged rafters or trusses, and structural alterations are escalated before repair

Critical item

Deck replacement pricing should not be used to conceal structural framing damage, significant deflection, cut or cracked framing, failed connections, or an undocumented field redesign that requires qualified evaluation or approval.

Replacement locations, quantities, materials, and price are verified before concealment

Critical item

Added decking should follow the signed allowance or change-order method with traceable location, count or area, approved product, unit price, credits, and authorization before underlayment covers the evidence.

Repairs, dryness, inspection status, and complete photo record support release to dry-in

Underlayment should begin only after deck corrections are complete, required inspections have passed or been documented, exposed work is dry enough for the selected materials, and the project record preserves concealed conditions.

Use this checklist immediately after tear-off exposes the roof deck and before underlayment or new roofing conceals it. It is not a structural engineering inspection. Do not walk a steep, wet, fragile, icy, or otherwise unsafe roof. Use ground-level observation, attic access where safe, dated contractor stage photos, permit inspections, and a qualified independent roof inspector when direct access is needed.

Reference standards

  • Approved plans and specifications, adopted state and local building code, permit and inspection conditions, authority having jurisdiction requirements, selected roof-system manufacturer installation instructions, and the signed contract
  • Approved sheathing or plank-deck requirements for the selected roof covering and manufacturer
  • Contract decking allowance, unit-price and change-order procedure, permit inspection requirements, and any engineer or designer repair detail
  • Tools

  • Signed contract, proposal, roof diagram or measurement report, product selections, permit, and approved change orders
  • Ground-level camera or binoculars, attic flashlight and moisture meter where safe, and dated contractor stage photos
  • Manufacturer installation and warranty documents plus inspection, delivery, invoice, and cleanup records