Window is set, supported, square, and fastened without distorting the frame
Critical itemAttachment should follow the product method and preserve drainage and operation.
A pre-trim window flashing checklist for jamb and head flashing, sill-pan outlet, weather-resistive barrier laps, head flashing or drip cap, compatible sealants, fin or frame fasteners, weeps, cladding clearances, interior air sealing, water-test planning, and photographic evidence before exterior trim or siding hides the assembly.
6 items to check
Attachment should follow the product method and preserve drainage and operation.
Flashing should connect the window to the drainage plane and direct upper water outward.
Drainage paths should not be sealed by foam, caulk, mortar, trim, or siding.
Products should adhere without chemical damage, loss of flexibility, or unsupported substitutions.
The opening should drain outward while limiting uncontrolled interior air leakage.
Concealment should wait until defects are corrected and evidence is saved.
Use after the window is set and flashed but before exterior trim, siding, stucco, or other cladding conceals the perimeter. Do not use unsafe ladders, walk roofs, remove structural support, or disturb lead, asbestos, or mold-containing assemblies. Require qualified building-envelope, structural, roofing, window, door, and siding professionals where appropriate.
A pre-setting window sill-pan checklist for approved pan type, positive drainage, end dams and back dam where required, corner continuity, substrate preparation, compatible primer and membrane, fastener and shim zones, integration with the weather-resistive barrier, weep path, cure, and photographic evidence.
Final inspection for replacement-window sizing, opening condition, support, fastening, flashing, drainage, air sealing, operation, glass, exterior and interior finishes, and documentation.
A pre-installation window rough-opening checklist for product and method, opening size and shape, sill support and slope, framing and structural condition, rot and moisture, sheathing, drainage-plane access, interior and exterior clearances, safety glazing and egress implications, and documented repairs before the window is set.
A pre-setting exterior-door sill-pan checklist for opening condition, support and level, pan slope and end dams, threshold bearing, drainage outlet, membrane continuity, jamb transitions, compatible sealants, fastener zones, accessibility and finish-height coordination, and documentation before the door frame conceals the sill.