Skip to content

Shower pan flood test before tile

A US job-site check for verifying a shower receptor or pan liner flood test before tile, setting bed, curb finish, or other cover-up hides the waterproofing.

7 items to check

BETA

These checklists are in development and testing. Information is for reference only and does not replace professional consultation. Data may contain inaccuracies. Consult a qualified professional.

If you notice an error, please email [email protected].

Inspection progress0 of 7
0%

Flood-test requirement and timing are confirmed

Critical item

The adopted plumbing code, local amendments, manufacturer instructions, and AHJ determine whether a flood test is required, how it must be witnessed or documented, and the required water depth and hold time. Do not substitute a quick hose spray for a required standing-water test.

Pan liner or membrane is complete before water

Critical item

A site-built receptor liner, bonded sheet membrane, liquid-applied membrane, hot mop, foam tray assembly, or other approved system should be installed as a complete waterproofing assembly before testing. Seams, corners, curb transitions, jamb returns, penetrations, and drain tie-in must follow the listed system and manufacturer instructions.

Drain plug tests the waterproof connection

Critical item

The waste line must be plugged watertight in a way that includes the receptor-to-drain waterproofing connection in the test. Traditional clamping drains, weep-hole drains, bonding flange drains, linear drains, and proprietary drains each need the plug location and method allowed by the product instructions and AHJ.

Threshold or temporary dam can hold the test water

Critical item

The test water level must meet the adopted code, manufacturer, and AHJ requirement without overflowing into adjacent construction. Curbless and low-threshold showers commonly need a temporary dam accepted by the AHJ and compatible with the waterproofing system.

Water level is marked for the required hold

Critical item

The receptor should hold the required standing water level for the AHJ, adopted code, and manufacturer-required test period with no evidence of leakage. Exact depth and duration are local and system dependent, so record the requirement instead of assuming one generic number.

Adjacent and below areas stay dry

Critical item

A passing flood test means no evidence of leakage at the receptor, curb, jambs, floor outside the shower, ceiling below, crawlspace, basement, subfloor, framing, or drain and waste connection visible from below.

Pass record is complete before cover-up

Do not cover the receptor with tile, setting bed, curb finish, lower backer-board cover-up, or other work that hides the test area until the required flood test has passed and any AHJ or manufacturer documentation is complete. Failed areas should be repaired, cured, and re-tested before cover-up.

Use this checklist after the shower receptor, pan liner, bonded sheet membrane, liquid-applied membrane, hot mop, foam tray, or other approved waterproofing assembly is complete and cured enough for testing, but before tile or other cover-up hides the receptor, drain connection, curb, jambs, and floor-to-wall transitions. Compare the work with the adopted IRC, IPC, UPC or state plumbing code, local amendments, approved plans, manufacturer instructions, TCNA/ANSI method, and the authority having jurisdiction.

Reference standards

  • Adopted IRC/IPC shower liner test and shower receptor provisions, using the local edition and section numbering
  • Adopted UPC or state plumbing code where that code governs the project
  • IRC/IPC receptor construction provisions for lined site-built receptors, bonded waterproof membranes, flanged drains, watertight drain connections, and weep-hole drains where applicable
  • TCNA Handbook shower receptor methods and ANSI A108/A118.10 where specified by the design, product listing, or manufacturer
  • Manufacturer installation instructions for the specific liner, liquid membrane, sheet membrane, foam tray, bonding flange, clamping drain, preformed receptor, sealant, and cure time
  • AHJ inspection card, correction notices, and local policy for flood-test depth, hold time, witness requirements, affidavits, and curbless temporary dams
  • Tools

  • Approved plans, permit card, AHJ notes, and product instructions
  • Correctly sized test plug, water source, bucket or hose, tape or pencil for water-level mark, flashlight, camera, towels
  • Access to the ceiling, crawlspace, basement, or adjacent room below the shower where available