Cimientos y bases de postes
Punto críticoCómo verificar
1. Verify footings are below local frost line
2. Check post bases — should be on metal brackets that hold wood above concrete
3. Verify post size is adequate (typically 6x6 minimum)
4. Check posts are plumb on all four sides
5. Verify spacing matches plans and is consistent
6. Check for proper concrete footing size (minimum 12" diameter)
Problemas frecuentes
- Posts buried directly in ground (rot risk)
- Footings above frost line (heaving)
- Undersized posts
- Posts not plumb
- Inconsistent spacing