Building drain and main sewer line
Critical itemPer UNI EN 12056 & DM 37/08, the building drain (horizontal pipe inside the building) must be minimum 3" for a single toilet, 4" for two or more toilets or the building sewer. Slope must be 1/4" per foot for 3" pipe, 1/8" per foot for 4" pipe. Pipe material must be approved (PVC Schedule 40, ABS, or cast iron). Cleanouts required every 100 feet and at every change of direction >45°.