Drywall and Plasterboard Inspection

Checklists for inspecting plasterboard (cartongesso) partition and lining systems in accordance with EN 520, EN 14195, EN 13950, UNI 11493 and NTC 2018.

6 items to check

BETA

These checklists are in development and testing. Information is for reference only and does not replace professional consultation. Data may contain inaccuracies. Consult a qualified professional.

If you notice an error, please email [email protected].

Inspection progress0 of 6
0%

Metal Framing Layout and Fixing

Critical item

In accordance with EN 14195 (metal framing components) and UNI 11493 (plasterboard systems — design and installation). Stud centres must match the design specification — typically 600 mm for standard partitions and 400 mm where enhanced performance is required. Floor and ceiling tracks must be fixed at maximum 600 mm centres per UNI 11493. NTC 2018 Chapter 4.5 applies for partitions acting as secondary structural elements in seismic zones.

Plasterboard Type and Specification

Critical item

In accordance with EN 520 (plasterboard types and classifications), EN 15283 (fibre-reinforced gypsum boards) and UNI 11493. Board types must match the project specification: Type A (standard), Type H1 (moisture-resistant for bathrooms per UNI 11493 Section 6), Type F (fire-resistant) or Type DF (fire and moisture). NTC 2018 Chapter 11 requires material traceability and CE marking.

Board Fixing and Screw Pattern

Critical item

In accordance with UNI 11493 and the system manufacturer's installation guide. Screws must be self-drilling, phosphated steel type, minimum 25 mm for single-layer and 35 mm for the outer layer of double-layer systems. Screw spacing: maximum 250 mm at board edges and 300 mm at intermediate studs per UNI 11493. EN 14566 specifies requirements for fasteners.

Joint Treatment and Surface Finishing

In accordance with UNI 11493 Section 8 and EN 13963 (jointing materials). Joint treatment must achieve the surface finish level specified by the designer: Level Q1 (basic for tiling), Q2 (standard for textured paint/wallpaper), Q3 (enhanced for matt paint) or Q4 (premium for gloss paint/critical lighting). Paper or fibreglass jointing tape must be embedded in the first coat of compound.

Acoustic Performance and Insulation Fill

Critical item

In accordance with D.P.C.M. 5/12/1997 (acoustic requirements for buildings), EN ISO 10140 (laboratory sound insulation measurement) and UNI 11493. Residential partitions between separate dwellings must achieve a minimum apparent sound reduction index R'w of 50 dB per D.P.C.M. 5/12/1997. Mineral wool infill density and thickness must match the tested system configuration.

Services Integration and Coordination

In accordance with UNI 11493, D.M. 37/2008 (installation of building services) and CEI 64-8 (electrical installations in buildings). All services (electrical conduits, plumbing pipes, HVAC ducts) within plasterboard systems must be installed before the second face is boarded. Penetrations through fire-rated partitions must be sealed with fire-stopping systems tested to EN 1366-3.