Skip to content

Drainage & Sewer System Inspection

Checklist for inspecting residential drainage and sewer system installation per DTU 60.11 & NF EN 12056.

5 items to check

BETA

These checklists are in development and testing. Information is for reference only and does not replace professional consultation. Data may contain inaccuracies. Consult a qualified professional.

If you notice an error, please email [email protected].

Inspection progress0 of 5
0%

Building drain and main sewer line

Critical item

Per DTU 60.11 & NF EN 12056, the building drain (horizontal pipe inside the building) must be minimum 3" for a single toilet, 4" for two or more toilets or the building sewer. Slope must be 1/4" per foot for 3" pipe, 1/8" per foot for 4" pipe. Pipe material must be approved (PVC Schedule 40, ABS, or cast iron). Cleanouts required every 100 feet and at every change of direction >45°.

Branch drain lines

Critical item

Per DTU 60.11 & NF EN 12056, branch drains must be sized for the fixture units they serve: 1.5" (1–3 DFU), 2" (4–8 DFU), 3" (20+ DFU with toilet). Every fixture must connect through a properly sized trap. Branch drains must slope minimum 1/4" per foot. Maximum horizontal distance from trap to vent per pipe size: 1.5" = 6', 2" = 8', 3" = 12'.

Vent system

Critical item

Per DTU 60.11 & NF EN 12056, every fixture trap must be vented. Main vent stack must extend through the roof (6" minimum above roof in normal climates, 12" in snow areas, 10' from any operable window). Vent must be minimum 1.25" for single fixture, 2" for bathroom group, 3" minimum for main stack. Vents must be installed to drain back to the drainage system by gravity.

Sewer lateral connection

Critical item

Per DTU 60.11 & NF EN 12056 and local sewer authority, the building sewer lateral must connect to the public sewer main at the proper depth and with approved fittings. Minimum pipe size is typically 4" (6" in some jurisdictions). Pipe material for the sewer lateral must be approved for below-grade use (PVC SDR 35, ductile iron). Backwater valve may be required in flood-prone or low-lying areas.

System testing

Critical item

Per DTU 60.11 & NF EN 12056, the complete DWV system must be tested before use. Air test: 5 PSI for 15 minutes. Water test: filled to highest point, 10' head minimum, 15 minutes. Camera inspection of sewer lateral recommended to verify no damage during construction. Final test must be witnessed by plumbing inspector before closing walls/floors.

Checklist for inspecting residential drainage and sewer system installation per DTU 60.11 & NF EN 12056.

Reference Standards

  • DTU 60.11 & NF EN 12056 — French plumbing standards
  • ASTM D2665 — PVC DWV pipe
  • ASTM D2661 — ABS DWV pipe
  • Local sewer authority requirements
  • Tools Needed

  • Level (for slope checking)
  • Sewer camera (for lateral inspection)
  • Air test gauge
  • Tape measure
  • Flashlight