Skip to content

Solar & Photovoltaic Systems Inspection

Checklist for inspecting solar photovoltaic installations per EN 62446, IEC 61215, IEC 61730, and EN 62548 standards.

7 items to check

BETA

These checklists are in development and testing. Information is for reference only and does not replace professional consultation. Data may contain inaccuracies. Consult a qualified professional.

If you notice an error, please email [email protected].

Inspection progress0 of 7
0%

Structural mounting

Critical item

Per EN 62548 Clause 4, the mounting system must be designed to support the PV array under all environmental loads including wind, snow, and dead loads per EN 1991-1-3 and EN 1991-1-4. The structural capacity of the roof or ground structure must be verified to carry the additional load of the PV system. Mounting fixings must be compatible with the roof covering material and must maintain the weatherproof integrity of the roof. All metallic components must be corrosion-resistant or protected to a standard suitable for the expected service life of at least 25 years.

Module installation

Per EN 62548 Clause 5, PV modules must comply with IEC 61215 (crystalline) or IEC 61646 (thin-film) for design qualification and IEC 61730 for safety qualification. Modules must be installed in accordance with the manufacturer's installation instructions, including orientation, tilt angle, and ventilation clearances. Module labels must be legible and data plate information must match the system design documentation. Modules must be handled and installed without mechanical damage to cells, frames, junction boxes, or cables.

DC wiring

Per EN 62548 Clause 7, DC cables must be double-insulated or equivalent (PV1-F type per EN 50618) and rated for the maximum system voltage including the cold-temperature Voc. Cable sizing must account for current-carrying capacity and voltage drop per EN 62548 Clause 7.3. DC connectors must be of the same manufacturer and type on both mating halves per EN 62548 Clause 7.2 — mixing connector brands is prohibited. String cables must be routed and secured to prevent mechanical damage, UV degradation, and heat exposure.

Inverter installation

Per EN 62548 Clause 8, inverters must comply with EN 62109-1 and EN 62109-2 for safety requirements. The inverter must be installed in a location with adequate ventilation to dissipate heat, protected from direct sunlight, rain, and dust as appropriate for its IP rating. DC and AC isolation switches must be provided per EN 62548 Clause 7.5. The inverter's input voltage and current ratings must be compatible with the string configuration. Anti-islanding protection must comply with EN 50549-1 for grid-connected systems.

AC connection

Per EN 62548 Clause 9 and HD 60364, the AC connection between the inverter and the distribution board must comply with standard low-voltage installation requirements. Cable sizing must account for the inverter maximum output current, installation method, and voltage drop per HD 60364-5-52. Overcurrent protection must be provided per HD 60364-4-43. The connection must be on the supply side of the main RCD or on a dedicated circuit with its own RCD per the grid operator's requirements. Generation metering must be installed where required.

Earthing and lightning protection

Per EN 62548 Clause 6, all exposed metalwork of the PV system including module frames, mounting structures, and cable trays must be earthed per HD 60364-5-54. Where the building has a lightning protection system (LPS), the PV system must be integrated per EN 62305-3 and EN 62305-4. Surge protection devices (SPDs) must be installed on both the DC and AC sides per EN 62305-4 and EN 62548 Clause 6.4 where a risk assessment indicates they are required. Equipotential bonding of the PV system to the building LPS must be provided.

Testing and commissioning

Per EN 62446-1, all PV systems must be tested and documented before handover. Required tests include continuity of earth bonding, string open-circuit voltage (Voc), string short-circuit current (Isc), string polarity, insulation resistance (minimum 1 MΩ per string at system voltage × 2 + 1000 V, or 500 V DC minimum), and functional testing of all protection devices. An as-built system documentation pack must be provided including string layouts, single-line diagrams, component datasheets, and all test results per EN 62446-1 Annex A.

Checklist for inspecting solar photovoltaic installations per EN 62446, IEC 61215, IEC 61730, and EN 62548 standards.

Reference Standards

  • EN 62446 — Photovoltaic (PV) systems — Requirements for testing, documentation and maintenance
  • IEC 61215 — Terrestrial photovoltaic (PV) modules — Design qualification and type approval
  • IEC 61730 — Photovoltaic (PV) module safety qualification
  • EN 62548 — Photovoltaic (PV) arrays — Design requirements
  • Tools Needed

  • IV curve tracer
  • Insulation resistance tester (1000 V DC minimum)
  • Irradiance meter (pyranometer)
  • Thermal imaging camera
  • Earth loop impedance tester
  • DC clamp meter